Project Status

Home / Projects

Project Execution Status

01

Environmental clearance of the project received in Feb., 2018.

02

'Commencement of works' ceremony of TFL inaugurated by Hon'ble Prime Minister in Sept., 2018.

03

Investment approval of the project has been accorded in Aug., 2019.

04

M/s Wuhuan Engg. Co. Ltd, China has been engaged as LSTK contractor for Coal Gasification and Ammonia/Urea packages of the project in Sept. 2019. Site activities has started.

05

Consent to Establish and Consent to Construct obtained.

06

Water has been allocated to the project in May 2020.

07

Construction water and construction power system charged and site has been handed over to M/s Wuhuan.

08

Concession Agreement for transfer of land executed by TFL and FCIL on 29th Jan. 2021.

09

Urea policy approved by CCEA on 20th April 2021.

10

Commitment of nearly Rs. 8500 cr. already done.

11

CISF has been inducted at TFL site.

Key Project Achievements

01 Nov 2020

90 MW Power Agreement

Agreement for 90 MW Power signed with OPTCL.

02 Apr 2021

Urea Policy Formulated

Urea policy for the project formulated by DoF.

03 Jun 2021

₹2,416 Cr Equity Approved

Complete upfront equity approved by project promoters.

04 Oct 2021

IOCL Pet Coke MoU

MoU signed with IOCL for supply of Pet Coke.

05 Dec 2022

₹9,000 Cr Debt Drawdown

Debt drawl of approximately ₹9,000 Cr commenced.

06 Apr 2023

Long-Term Coal Linkage

Long-term coal linkage successfully allocated.

07 Apr 2023

Ash Void Allocation

Ash void successfully allocated for the project.

08 Dec 2023

GAIL Gas Agreement

Natural Gas sale agreement signed with M/s GAIL.